Development progress release 2.2


These progress bars monitor the progress on the epics planned for the next release. Progress is measured based on backlog completion, but also on subjective estimation of the Product Owner. Colours are obvious and show if the epic is lagging behind (red), should be mostly implemented (yellow) or will be fully implemented (green).

2.1 New brain simulators
90%
2.1 Frontend redesign
90%
2.1 Workflow redesign
90%
2.1 Data persistence
100%
2.1 Piz Daint step 1
90%
2.2 CLE refactoring
0%
2.2 Record & replay
90%
2.2 CDP1/Ijspeert school
10%
2.2 SP6/SP10 prototype
10%
2.2 Piz Daint step 2
100%